Etches Park Depot - EPIU Automatic Measuring System (AMS) Installation

Completed wheel and brake monitoring installation at Derby Etches Park Depot
Projects / Derby Etches Park Depot – Wheel and Brake Monitoring Installation
Wabtec / East Midlands Railway · Rail

Derby Etches Park Depot – Wheel and Brake Monitoring Installation

Client
Wabtec, for East Midlands Railway
Location
Derby, England
Sector
Rail
Year of construction
2026

The problem

East Midlands Railway required automated wheel and brake monitoring at its Derby Etches Park depot, to streamline fleet inspections, reduce manual intervention and increase depot throughput. Wabtec was appointed to deliver the wider scope of works for EMR, and RCA Construction was engaged to deliver the civil engineering and installation works needed to integrate the new diagnostic equipment within an operational depot.

Our approach

Working on behalf of Wabtec, RCA Construction installed the monitoring equipment alongside a package of civil and safety improvements:

  • KinetiX WheelView®: Precision imaging for wheel profile and condition monitoring.
  • KinetiX BrakeView® – Disc: Automated inspection of brake disc integrity.
  • KinetiX BrakeView® – Pad: Sensors to monitor brake pad wear and performance.
  • Troughing routes: Cable management for the depot’s electrical and data needs, including hollow sleepers to accommodate track cable crossings.
  • GRP walkways: Lightweight, slip-resistant walkways to improve access for depot staff.
  • Handrail systems: Safety barriers to provide a safe working environment around the new equipment.

The works were planned with the depot around its daily operations, with a dedicated team on site to keep disruption to a minimum.

The outcome

The monitoring equipment and associated civil works were completed in 2026, giving East Midlands Railway automated, real-time monitoring of rolling stock health at Etches Park, together with improved access and safety for depot staff.

Gallery

Planning a similar project?

Contact us

The Challenge

GTR Rail identified the need to replace its aging underground wheel lathe at Selhurst Depot, Europe’s largest and busiest rail depot. The existing lathe had reached the end of its service life, and the new installation had to meet the growing operational demands of the Gatwick Express service, which transports approximately 21 million passengers annually.

Objectives

  • Install a new tandem wheel lathe pit with an integrated inspection pit.

  • Minimise disruption to depot operations and Gatwick Express services.

  • Ensure strict environmental controls for noise, dust, and fumes during construction.

Challenges

  1. Access Restrictions: Selhurst Depot has a single access road that could not be blocked by construction traffic.

  2. Operational Continuity: Downtime had to be kept to an absolute minimum to maintain service reliability.

  3. Environmental Sensitivity: The work zone was adjacent to the paint shop and repair road, requiring stringent controls on noise, dust, and fumes.

Our Solution

RCA leveraged its extensive experience with wheel lathe projects to develop a comprehensive plan:

  • Installed a network of fume sensors and noise monitoring equipment.

  • Erected scaffolding with dust-suppression sheeting to protect sensitive areas.

  • Produced a detailed traffic management plan and a rolling two-week lookahead schedule to avoid conflicts with depot activities.

  • Utilised advanced 3D modelling for precise planning and execution.

The Result

RCA delivered a modern, efficient wheel lathe system that meets current and future demand. Additionally:

  • The project was completed within a 10 month timeframe.

  • Zero noise or dust complaints during construction.

  • No disruption to Gatwick Express operations

Key Takeaways

  • Early and detailed planning is critical for projects in high-traffic, operational environments.

  • Collaboration with depot management and use of advanced modelling tools can significantly reduce risk and downtime.

  • Environmental controls are essential for maintaining safety and operational integrity during construction.